MV Alfred 85m RoRo Ferry
Location
UK and European Operations
Client
Strategic Marine (Vietnam)
H&V Design
Kelvin Ross Engineering
Contract Scope
Design, procurement and commissioning of the accommodation ventilation and heating systems.
Zoned ventilation plants with winter/summer variable capacities for passenger accommodation. Heating provided by central hot water boilers, with distribution pipework serving the ventilation plant heating coils supplementary ceiling mounted or bulkhead mounted fan convectors.
Ventilation systems are installed to serve areas such as passenger saloons, wheelhouse, crew accommodation, auxiliary machinery spaces, toilets, galley, laundry, etc.
Construction in Vietnam and operating between Scotland and Orkney Islands.
Contract Value
£200,000
Ship Completion
July 2019
Contract Period
18 Months